Follow us:WhatsappFacebookTwitterTelegram.cls-1{fill:#4d4d4d;}.cls-2{fill:#fff;}Google NewsThe delay in the commissioning of the Koodankulam Nuclear Power Project (KKNPP) is likely to cost the KSEB dear - by as much as Rs 100 crore this financial year in power purchases, according to the power utility. This is largely due to a mistaken calculation by the State Electricity Regulatory Commission that the KSEB would start receiving Koodankulam power during 2012-2013, the KSEB has said in a petition seeking the review of an April 2012 Commission decision chopping KSEB’s revenue gap by Rs 1351.10 crore. While filing its annual ARR & ERC petition, the KSEB had ignored KKNPP power since its commissioning was mired in uncertainty. But the Commission, in approving the petition with revisions, assumed that Unit I of KKNPP will be commissioned by August 2012 and Unit II by December 2012.The commission estimated that the KSEB would receive 665 million units (MU) Koodankulam power the current fiscal. ‘‘However, the schedule of the commissioning of the Koodankulam plant is yet to be finalised and the synchronisation of Unit I is yet to start.‘‘Nuclear power plants usually require three to four months for declaring the commercial operation from the date of synchronisation. Hence, there is very remote chance for the commissioning of the plant, especially the second unit, during this financial year,’’ the KSEB noted.  For KSEB, the problem lies in that the Commission estimated KKNPP power to be available at Rs 3.19 per unit. But now, the KSEB will have to look at liquid power stations and power traders for meeting the KKNPP shortfall. And this power will not come cheap. According to current data on the Nuclear Power Corporation of India Ltd (NPCIL) website, KKNPP Unit I will be commissioned in August this year, but Unit II will start operations only by March 2013. Kerala’s KKNPP quota is 266 megawatts (MW).first published:January 01, 1970, 05:30 ISTlast updated:January 01, 1970, 05:30 IST 
window._taboola = window._taboola || [];_taboola.push({mode: 'thumbnails-a', container: 'taboola-below-article-thumbnails', placement: 'Below Article Thumbnails', target_type: 'mix' });Latest News

The delay in the commissioning of the Koodankulam Nuclear Power Project (KKNPP) is likely to cost the KSEB dear - by as much as Rs 100 crore this financial year in power purchases, according to the power utility.

 This is largely due to a mistaken calculation by the State Electricity Regulatory Commission that the KSEB would start receiving Koodankulam power during 2012-2013, the KSEB has said in a petition seeking the review of an April 2012 Commission decision chopping KSEB’s revenue gap by Rs 1351.10 crore. 

While filing its annual ARR & ERC petition, the KSEB had ignored KKNPP power since its commissioning was mired in uncertainty. But the Commission, in approving the petition with revisions, assumed that Unit I of KKNPP will be commissioned by August 2012 and Unit II by December 2012.

The commission estimated that the KSEB would receive 665 million units (MU) Koodankulam power the current fiscal.

 ‘‘However, the schedule of the commissioning of the Koodankulam plant is yet to be finalised and the synchronisation of Unit I is yet to start.

‘‘Nuclear power plants usually require three to four months for declaring the commercial operation from the date of synchronisation. Hence, there is very remote chance for the commissioning of the plant, especially the second unit, during this financial year,’’ the KSEB noted.  For KSEB, the problem lies in that the Commission estimated KKNPP power to be available at Rs 3.19 per unit. But now, the KSEB will have to look at liquid power stations and power traders for meeting the KKNPP shortfall. And this power will not come cheap.

 According to current data on the Nuclear Power Corporation of India Ltd (NPCIL) website, KKNPP Unit I will be commissioned in August this year, but Unit II will start operations only by March 2013. Kerala’s KKNPP quota is 266 megawatts (MW).